Welcome
The Florida Department of Transportation (FDOT) District IV has commenced the Design Phase for County Road (CR) 510 in Indian River County from CR 512 to 58 Avenue. This corridor is critical in facilitating the west to east movement of traffic in Indian River County as it connects Interstate 95 (I-95) to State Road (SR) A1A. This Design Project is for the widening of CR 510 from two lanes to four lanes, in order to address the future capacity and operational and safety needs of the roadway. This Design Project has been divided into four segments. A Project Development and Environment (PD&E) Study for CR 510 from 58th Avenue to East of US-1 began in 2022.
| Segment 5 | Segment 6 | Segment 7 | Segment 8 | CR 510 PD&E Study |
| From West of 82nd Avenue to Powerline Road | From Powerline Road to 58th Avenue | From CR 512 to 87th Street | From 87th Street to West of 82nd Avenue | From 58th Avenue to East of US-1 |
| FM# 405606-5 | FM# 405606-6 | FM# 405606-7 | FM# 405606-8 | FM# 441692-1 |
Upcoming Public Meetings
The most recent Public Meeting for Segment 405606-8 was held was held in person on Wednesday, August 2, 2023, and virtually on Thursday, August 3, 2023.
Related Links
How to Use a Roundabout – Click Here
Design Project Segments At-a-Glance
| District Four (Southeast Florida) | Project Manager Ron Wallace, P.E., |
| Design Date May 2018 | Right-of-way Appraisal and Acquisition Begin Summer 2028 |
| Construction Cost $30,452,017 | Lengths and Limits
From West of 82nd Avenue to Powerline Road |
| Design Date May 2018 | Right-of-way Appraisal and Acquisition Begin Summer 2028 |
| Construction Cost $20,718,614 | Lengths and Limits
From Powerline Road to 58th Avenue |
| Construction Start Date
December 2024 | Est. Construction Completion Fall 2027 |
| Construction Cost $13,038,720 | Lengths and Limits
From CR 512 to 87th Street |
| Construction Start Date
Fall 2029 | Est. Construction Completion Date
Fall 2031 |
| Construction Est. Cost $14,421,597 | Lengths and Limits
From 87th Street to West of 82nd Avenue |