Conflict of Interests - Frequently Asked Questions
Overview:
Consultants representing the Department must be free of conflicting professional or personal interests. In order to prevent potential conflicts of interest, the Department has established guidelines to be followed by professional services Consultants. Please familiarize yourself with the requirements of Procedure No. 375-030-006, also known as: "Restriction on Consultants' Eligibility to Compete for Department Contracts". By submitting a Letter of Response, the Consultant certifies that they are in compliance with Procedure No. 375-030-006. This procedure is available at the following link: Professional Services Publications Menu
In addition to the restrictions identified in Procedure No. 375-030-006, please be advised of the following prohibition: A consultant firm or its affiliate who was the Designer or Engineer of Record is precluded from bidding on the same project as the construction contractor, or as a member of the construction contractor's team (subcontractor).
The Design-Build Procurement & Administration Procedure (No. 625-020-010) includes the following prohibition on pg. 39: The Design/Build firm may not participate in preparation of the NEPA documentation as this would be a conflict of interest.
The Design/Build Procurement Procedure can be accessed at the following link:
625-020-010 Design-Build Procurement & Administration
Information on DRB conflict of interest relationships can be found at the following link:
http://www.fdot.gov/construction/CONSTADM/DRB/DRBMain.shtm
General Consultant Services Conflict FAQs | ||
Questions | Quick Guidance | View Details |
1. If a Designer uses a Contractor to perform constructability reviews on a design contract, does this preclude the Contractor from pursuing the construction project? | Yes | Detailed Guidance |
2. The Department hires an inspector to perform verification inspections, and the same inspector will also be performing plant certification inspections for another company. If a Plant Certification Agency uses the other company to perform their plant certification inspections, is it a conflict of interest if the same inspector performs the plant verification inspection for the Department? | No | Detailed Guidance |
3. Are consultants that perform Value Engineering (VE) on projects excluded from further work on the project? | No | Detailed Guidance |
4. Can a Geotechnical Consultant who provides geotech design services be permitted to later provide unrelated CEI services on the same project? | Yes, if services are unrelated. | Detailed Guidance |
5. Is it a conflict for a firm to perform preliminary pavement coring and then later perform Contractor Quality Control (CQC), Geotechnical, or engineering services? | No, the coring data can be viewed as unrelated | Detailed Guidance |
6. On a Design/Bid/Build project, can a sub to the Engineer of Record (EOR) for survey work also become a sub to the CEI for survey work? | District Secretary Decision | Detailed Guidance |
6a. Can a Consultant firm performing work for or representing a developer, private land owner, or business on a project, seek employment from the Department on the same project? If yes, any restriction in capacity? | No. This would be a conflict, regardless of capacity. | |
6b. Can a Consultant firm performing work for or representing a local agency (i.e City of Jax Beach, Jacksonville Transportation Authority, etc) on a project also seek employment from the Department on the same project? If yes, any restriction in capacity? | No. This would be a conflict, regardless of capacity. | |
7. Can a consultant firm, or its affiliate, that is the Engineer of Record (EOR) on a project be considered eligible to compete as a prime consultant for CEI services on that same project. | No | Detailed Guidance |
7a. The same consultant firm is prohibited from performing both the design and the CEI on the same project. Does this also apply to a Local Agency Program? | Yes, it is still viewed as a conflict. | Detailed Guidance |
8. On a CEI contract, a proposed Project Administrator is related (by marriage) to the contractor on that job. Is this a conflict of interest? | Yes | Detailed Guidance |
9. Would a design firm pursuing a CEI Hybrid contract have a conflict of interest if the firm performed all (or part) of the design of a project on which the inspectors would be assigned? | No | Detailed Guidance |
10. Can a Geotechnical Consultant that provided geotechnical design services for the foundation design on a Design-Bid-Build project be later retained by the Department to perform dynamic load test measurements and analysis of test piles on the same project? | Yes | Detailed Guidance |
General Contractor Services Conflict FAQs | ||
Questions | Quick Guidance | View Details |
1. If a Contractor participates in a Value Engineering Study Workshop or Cost Risk Analysis Workshop, does this preclude the Contractor from pursuing the construction project? | Yes | Detailed Guidance |
Design-Build Related Conflict FAQs | ||
Questions | Quick Guidance | View Details |
General Guidance (includes example using P3 project) | ||
1. Can a consultant that performs PD&E services on a given project participate on the design-build services? | Yes | Detailed Guidance |
2. If a consultant firm performs the initial and/or final design (after NEPA Record of Decision), are they able to participate on the design-build for the project? | District Secretary Decision | Detailed Guidance |
3. This question is related to mechanical & electrical inspection staffing/availability as it relates to CEI services on a Design-Build type contract involving a movable bridge. Can the engineering firm providing the services for writing part of the RFP be part of a CEI team? | No | Detailed Guidance |
4. Can a firm who performed only preliminary estimating services as a sub on a Design-Build contract pursue CEI work on the same contract as a sub? | No | Detailed Guidance |
5. If a firm provides FDOT input into the development of a RFP, can they subsequently, after the contract is awarded, be added to the awarded contractors team (e.g. as a sub-consultant)? | No | Detailed Guidance |
6. Can a consultant preparing a Design-Build Criteria Package for a particular project also provide CEI services for the same project since they will not be EOR for the project? | No | Detailed Guidance |
7. Would a firm reviewing a Design-Build Criteria package on behalf of FDOT be precluded from pursuing the Design-Build project as the designer? | No | Detailed Guidance |
8. Can a lead designer on one design-build team also serve as a sub-consultant on another design-build team on the same project? | Yes, they must disclose this to the second firm. | Detailed Guidance |
9. Would it be a conflict of interest for a firm to participate on a Design-Build team if they had previously performed hydraulic and scour work at the same project location? | No. Due to limited work & no input on RFP. | Detailed Guidance |
10. A Design-Build team has the original EOR for the design plans on their team, would this be considered a conflict of interest? | Yes, unless District Secretary approves. | Detailed Guidance |
11. A firm participated as a sub-consultant with minor involvement during plans preparation for a Design-Build project. Can this involvement be considered a conflict and keep them from participating on a Design-Build team for the project? | Yes, must receive exemption from District Secretary to participate | Detailed Guidance |
12. If a firm performs soil borings at a location of a future Design-Build project, will they be ineligible to participate as a geotechnical sub-consultant on a DB team for that project? | Depends on level of involvement. Would need approval. | Detailed Guidance |
13. Can a consultant be on both the Design-Build team and a CEI team for the same project? | No | Detailed Guidance |
14. Can a firm participate on a Design-Build Team if they participated in the development of a standard design that will be utilized on the design-build project? | Yes | Detailed Guidance |
15. Can a GEC employee, who also works as a subconsultant for a consultant that is pursuing DB contracts, be allowed to participate in any ATCs where that consultant is a proposer? | No | |
Dispute Review Board Conflict FAQs | ||
Questions | Quick Guidance | View Details |
1. I am a member on an active DRB and the CEI firm for that contract asks me to perform constructability reviews during the design phase. Is it a conflict of interest for me to participate on the design contract with the CEI firm? | Divulge potential conflict for review by FDOT/Contractor/Board Members | Detailed Guidance |
Public Private Partnerships (P3) Conflict FAQs | ||
Questions | Quick Guidance | View Details |
1. Could the consultant acting as the owner’s rep in writing the P3 RFP also be the consultant performing the Department’s Oversight CEI? | No | |