Design Build Specifications - January - June 2014
Design-Build Boiler-Plate
January - June 2014
The Design-Build Boilerplate* is the Division I Master Document to be used in the Request for Proposal (RFP) for Design-Build projects.
Design Build Pick-List
NOTE: The files below contain optional text which may be incorporated into
the Design-Build Boilerplate for inclusion into the RFP, to create specific Contract language.
File | Title | Usage Notes |
---|---|---|
To Change Award and Execution Time | ||
SP0030200 | Award and Execution of Contract | When necessary to change standard "Award and Execution" |
Design Build Finance | ||
SP0030600DBF | Execution of Contract and Bond | Use on Design Build Finance projects |
Structures Over 1500 Feet in Length (over water) | ||
SP0050901 | Inspection | Long bridge jobs (1500 feet or longer); modify to suit |
Preference to State Residents | ||
SP0072700 | Preference to State Residents | All Non-Federal Aid Projects |
Legal Requirements and Responsibility to the Public - Title VI Assurance - DOT 1050.2, Appendix A | ||
Toll Facility (Turnpike Enterprise Only) | ||
SP0070201TP-711 | Permits and Licenses (No free passes will be issued to the Contractor for use on the Toll Facility) | All Turnpike Enterprise Jobs. |
Operations Within Railroad Right-of-Way | ||
SP0071104 | Operations within CSX Railroad Right-of-Way | Use on Projects involving CSX Transportation. |
Partnering | ||
SP0080306 | Prosecution of Work - Partnering | 999-16 |
Disputes Review Board | ||
SP0080307RDRB | Regional Disputes Review Board | Jobs without Pay Item No. 999-20 |
Jobs with Lighting | ||
SP0080409 | Contaminated Material - Mercury-Containing Devices and Lamps | Jobs with lighting. |
Damage Recovery | ||
SP0081300 | Damage Recovery | Use when requested by the District Construction Engineer. (Do not use with Lane Rental.) |
Alternative Bidding | ||
SP0081300A | Prosecution and Progress | All Jobs with Alternative Bidding. Use with the approval of the District Construction Engineer. |
SP0081300B | "Bonus" Payment and Waiver of Contractor Claims - Date Specific | Bonus (Date Specific) Use with the approval of the District Construction Engineer. |
SP0081300BCD | "Bonus" Payment and Waiver of Contractor Claims - Calendar Day | Bonus (Calendar Days) Use with the approval of the District Construction Engineer. |
SP0081300MB | "Bonus" Payment and Waiver of Contractor Claims - Milestone | Milestone Bonus. Use with the approval of the District Construction Engineer. Do not use with SP00813000B or SP0081300BCD. |
SP0081300LQS | Liquidated Savings for Early Completion | Liquidated Savings. Use with the approval of the District Construction Engineer. |
SP0081300ID | Incentive - Disincentive | Incentive - Disincentive. Use with the approval of the District Construction Engineer. |
SP0081300MID | Incentive - Disincentive - Milestone | Milestone Incentive - Disincentive. Use with the approval of the District Construction Engineer.. Do not use with SP0081300ID) |
Design Build Attachments to the RFP
NOTE: The files below may be added to the RFP as attachments, when required.
DIVISION I CHANGES | ||
SP0073000 | Title VI Assurance | All Federal Aid Projects (Mandatory # 1 - 3/14 Implementation) |
DIVISION II CHANGES | ||
SP1050813DB | Contractor Quality Control General Requirements | Use when Geotechnical Services are required for the project. |
SP4550000DB | Structures Foundations | Use when Geotechnical Services are required for the project. |
VALUE ADDED DEVELOPMENTAL SPECS | ||
DEV475 | Value Added Bridge Components | Use when requested and approved by the District Construction Engineer. |
DEV725 | Value Added Highway Lighting System | Use when requested and approved by the District Construction Engineer. |