Project Description
The project involves the reconstruction of State Road (SR) 710/Warfield Boulevard from SW Fox Brown Road (MP 8.9) to SW Allapattah Road (MP 14.872) in Martin County, Florida. The overall project length is within the Village of Indiantown.
Within the project limits, SR 710/SW Warfield Boulevard is a two-lane (one lane in each direction), undivided roadway with a painted median and a posted speed limit of 35-60 mph. The corridor includes 12 ft travel lanes with flushed shoulders. SR 710/Warfield Boulevard is a strategic intermodal system (SIS) facility with a functional classification of urban rural principal arterial and context classification of C3C -Suburban Commercial.
The proposed improvements include widening of the existing roadway from a two-lane divided roadway to a four-lane divided roadway with raised median. The proposed typical section includes two 12-ft lanes in each direction separated by a 22-ft raised median with curb and gutter on both sides of the roadway. A 10-ft shared use path is provided on the north side of the roadway. In addition, the intersection at SW Allapattah Road as well as the new proposed Garcia Drive connection for the Terra Largo Development will be signalized to enhance safety.
Project Objectives
The objective of this project is to provide capacity improvements to enhance mobility, safety, emergency access and truck movement within Martin County. The proposed SR 710 corridor capacity improvements project will include:
- Widen S.R. 710 from a two-lane undivided roadway to a four-lane divided roadway
- Construct a curbed median with flush shoulders from SW Fox Brown Road to west of SW Dr. Martin Luther King Drive
- Provide curb and gutter on both sides of the roadway from west of SW Dr. Martin Luther King Drive to SW Allapattah Road
- Construct a 12-foot-wide shared-use path along the north side of the roadway throughout the project limits
- Upgrade the existing drainage system to accommodate the proposed roadway improvements
- Install a new traffic signal at the intersection of S.R. 710/Warfield Boulevard and SW Allapattah Road
- Install corridor lighting from SW Dr. Martin Luther King Drive to SW Allapattah Road, as well as at major intersections within the project limits
Benefits
Project Schedule
| Begin Project: | 05/31/2024 |
|---|---|
| Public Workshop: | 09/15/2026 |
| ROW Certification: | 02/04/2027 |
| Production: | 09/07/2027 |
| Letting Date: | 01/01/2031 |
Project Contact Information
Robert Lopes, P.E.
Florida Department of Transportation (FDOT) Project Manager
FDOT District Four
3400 West Commercial Boulevard
Fort Lauderdale, FL 33309
Email: [email protected]
Telephone: (954) 777-4425
Project Updates
Sign up for project updates! Click here to complete SR 710 Capacity Improvement contact form to receive important project updates.
