Project Description

The project involves the reconstruction of State Road (SR) 710/Warfield Boulevard from SW Fox Brown Road (MP 8.9) to SW Allapattah Road (MP 14.872) in Martin County, Florida. The overall project length is within the Village of Indiantown.

Within the project limits, SR 710/SW Warfield Boulevard is a two-lane (one lane in each direction), undivided roadway with a painted median and a posted speed limit of 35-60 mph. The corridor includes 12 ft travel lanes with flushed shoulders. SR 710/Warfield Boulevard is a strategic intermodal system (SIS) facility with a functional classification of urban rural principal arterial and context classification of C3C -Suburban Commercial.

The proposed improvements include widening of the existing roadway from a two-lane undivided roadway to a four-lane divided roadway with median. The proposed typical section includes two 12-ft lanes in each direction separated by a 22-ft median with flush shoulders on both sides of the roadway. A 10-ft shared use path is provided on the north side of the roadway. In addition, the intersection at SW Allapattah Road will be signalized to enhance safety.

Project Objectives

The objective of this project is to provide capacity improvements to enhance mobility, safety, emergency access and truck movement within Martin County. The proposed SR 710 corridor capacity improvements project will include:

  • Widening from a 2-lane undivided roadway to a 4-lane divided roadway with medians
  • Provision of a 10-ft shared use path on the northside of the roadway
  • Signalization of the SW Allapattah Road
  • Provision of new corridor lighting within the project limits
  • Drainage improvements to accommodate the additional impervious area

Benefits

Enhance safety along the project corridor
Increase capacity and reduce congestion
Improve emergency response time
Accommodate pedestrians and cyclists along the shared use path

Project Schedule

Begin Project:05/31/2024
Public Workshop:01/29/2027
ROW Certification:02/04/2027
Production:09/07/2027
Letting Date:01/01/2031

Project Contact Information

Robert Lopes, P.E.
Florida Department of Transportation (FDOT) Project Manager
FDOT District Four
3400 West Commercial Boulevard
Fort Lauderdale, FL 33309
Email: [email protected]
Telephone: (954) 777-4425

Project Updates

Sign up for project updates! Click here to complete SR 710 Capacity Improvement contact form to receive important project updates.