June 1 to June 30, 2022

Project Progress: 15% of time elapsed

Major Activities:

  • Installing foundations for the replacement bridge’s main bascule piers
  • Removing the existing bulkhead on the north shore of the Intracoastal Waterway
  • Removing debris from the waterway
  • Relocating utilities (by others)
  • Installing underground conduits for Intelligent Transportation System devices
  • Reconfiguring the Old Dixie Highway and Alternate A1A intersection
  • Placing concrete seal slab around the pile foundations at the north bascule pier
  • Installing the steel bulkhead at the northwest corner of the existing bridge
  • Continuing minor repairs at the Alternate A1A Bridge
Restrictions:
  • The southbound merge lane from Old Dixie Highway to southbound Alternate A1A will be closed continuously through June 30 with traffic diverted to the left-turn lane from Old Dixie Highway to northbound Alternate A1A. The left-turn lane will become a dual right- and left-turn lane from Old Dixie Highway to Alternate A1A.
  • Lane closures may occur from 9 p.m. to 6 a.m. Sunday through Saturday on US 1, Indiantown Road, Alternate A1A and Old Dixie Highway.
  • Intermittent daytime lane closures may occur on Alternate A1A and US 1 from 9 a.m. to 4 p.m.
  • Continuous lane closures may occur in both directions on Alternate A1A between US 1 and Old Dixie Highway.
  • The southbound movement from Old Dixie Highway to Alternate A1A may be diverted.
  • The western sidewalk along US 1 from CR A1A to south of the US 1 Bridge is closed until further notice.