County Road (C.R.) 713/SW High Meadow Ave from I-95 to C.R. 714/SW Martin Hwy
Welcome
The Florida Department of Transportation (FDOT) has completed a Project Development and Environment (PD&E) Study for County Road (C.R.) 713/SW High Meadow Ave from I-95 to C.R. 714/SW Martin Hwy in Martin County, Florida and the Location Design Concept Acceptance was obtained on September 14, 2025.
The purpose of the project is to improve capacity for local and regional travel, freight movement, emergency evacuation and to enhance economic development in northeast Martin County.
The capacity needed for the project is based on the implications of traffic projections. If no improvements are proposed, the congestion on the corridor will significantly worsen and result in prolonged delays for residents, regional travel, and the 6% truck/freight traffic exchange between I-95 and the nearby Turnpike Interchange. The I-95 ramps are located on the south end of SW High Meadow Avenue. The Turnpike Interchange is located west of SW High Meadow Ave at the intersection of SW Martin Highway and SW Martin Downs Blvd.
The transportation demand is based on the projected increase of Martin County from 158,431 in 2020 to 193,300 in 2045 which will cause an increase in the work-related, recreational, and freight trips in the region.
The social and economic development demand comes from the existing residential land use on the east side of the project, the existing developments, and the proposed developments. A review of the proposed Martin County developments includes Palm Pike Crossing, a development that includes a gas station and 27.5 acres of retail development located on the northwest section of the project.
As a result, the project will improve capacity to help accommodate planned development in the area and improve regional access to I-95.
Project Update
Financial Project ID: 441699-1-58-01
The project has moved to the DESIGN PHASE as of October 2025 and it is in its Initial Engineering Design stage. The Project Schedule timeline is as follows:
-
Initial Engineering (30% Plans) Submittal
-
Right of Way Phase Begin
-
Constructability (60% Plans) Submittal
-
Public Information Meeting
-
Biddability (90% Plans) Submittal
-
Design Complete (Production)
For questions, please contact:
Damaris Williams, P.E.
FDOT Design Project Manager
3400 West Commercial Boulevard
Fort Lauderdale, FL 33309
Tel:
954-777-4679
Toll-Free:
866-336-8435 ext. 4679
Email:
[email protected]
For more information about the PD&E, please see below.
Project Development & Environment (PD&E) Study
FPID: 441699-1-22-02
Federal Aid Project Number: TBD
ETDM Number: 14501
What is a PD&E Study?
A PD&E Study is FDOT's procedure for complying with the National Environmental Policy Act (NEPA) of 1969, and associated federal and state laws and regulations. During this phase, FDOT performs preliminary engineering, evaluates the project's impacts to the social, cultural, natural, and physical environments, completes interagency coordination, and engages the public. Public involvement is a key aspect throughout the life of a project. The objectives of a PD&E Study are to support decisions concerning if, where, and what should be built to address the identified transportation needs.
Project Phases
- 1 Planning
- 2 Project Development and Environment (PD&E) Study If needed
- 3 Design Current Project Phase
- 4 Right of Way Acquisition If needed
- 5 Construction
- 6 Maintenance
Why it's done:
- Evaluate project feasibility and potential environmental impacts (natural, physical, social, cultural)
- Comply with federal and state environmental laws
- Secure federal regulatory approval
What it involves:
- Conducting preliminary engineering
- Evaluating options to avoid, minimize or mitigate potential environmental impacts
- Coordinating with federal, state and local agencies
- Engaging the public in project development
- Selecting a preferred alternative for Final Design
For questions relating to Traffic Noise, click here.
Public Hearing
The Public Hearing was held on Wednesday, May 14, 2025 at 5:30 p.m. (Virtual through GoToWebinar), and Thursday, May 15, 2025 at 5:30 p.m. (In-Person at the Palm City Community Center).
To view a recording of the Public Hearing, click here.
All exhibits presented at the Public Hearing are available on the Documents and Publications page.
Alternatives Public Workshop
The Alternatives Public Workshop was held on Tuesday, June 25, 2024 (Virtual), and Thursday, June 27, 2024 (In-Person).
To view a recording of the Alternatives Public Workshop, click here.
For additional information, view the Documents and Publications page.
Public Kick-Off Meeting
The Public Kick-Off Meeting was held on Tuesday, February 13, 2024 (Virtual), and Thursday, February 15, 2024 (In-Person).
To view a recording of the Public Kick-Off Meeting, click here.
For additional information, view the Documents and Publications page.
Steven C. Braun
District 4 Secretary
3400 W Commercial Blvd.
Fort Lauderdale, FL 33309
Tel: 954-777-4100
Toll Free: 1-866-336-8435
Fax: 850-414-4221
E-Mail Us
Additional Contacts
Staff Directory