Date | FIN# | Contract | Subject | A/R/P |
1/6/22 | 43273425201 & 43273425202 | E7R18 | I-75 Overpass Road Interchange | A |
| | | | |
4/19/21 | 43057315201 | T7412 | Diverging Diamond Interchange | R |
3/5/21 | 44383315201 | E7N02 | Orlando R&B Bearing Pad Payment | A |
2/2/21 | 40582225201 | T7383 | US10 SR55 W. Green Acres to Jump Court Citrus County, FL | A |
1/6/20 | 41656125201 | T7388 | SR 54 Reconstruction | A |
5/5/16 | 42896215201 42896215202 42456135201 42456145201 | T7331 | Milling and Resurfacing of State Road 60 (Courtney Campbell Causeway) | A |
1/26/15 | 25558515201 | T7145 | SR 39 (Alexander St. N.) Plan Quantities for Embankment and Excavation | A |
6/27/14 | 25866025201 | T7298 | SR 93 (I275) Temporary Barrier Wall Payment | A |
3/11/14 | 41602617219 | E7H16 | SR 54 - Method of Repair for Pavement Deficiency (SDRB) | A |
3/12/13 | 41881115201 | E7G26 | Tampa Bay Trail Underpass at Sheldon Rd - Construct Critical Temporary Wall | A |
1/27/12 | 41684225201 | E7G19 | SR 43 (US 301) Subcontractor Asphalt Straightedge Claim | A |
7/25/11 | 41340715201 | T7189 | SR 580 (Bush Blvd) - Entitlement to Compensation on Several Pay Items | A |
5/2/11 | 41133715201 | T7164 | SR 600/US 92 - Method of Payment for Boardwalk Support Posts | A |
4/16/11 | 42616115201 | T7258 | SR 597 (Dale Mabry) - Quantity of Structural Treated Timber | A |
1/30/09 | 25715415201 | T7147 | SR 688 (Ulmerton Road) - Installation of Drilled Shafts due to Differing Site Conditions | A |
| | | | |
8/24/05 | 25695715201 | 21562 | SR 55 (US 19) Removal of Unsuitable Material to Install Sanitary Sewer line | A |
10/13/04 | 25695715201 | 21562 | SR 55 (US19) Additional Sign Structure Luminaries | A |
12/10/03 | 25695715201 | 21562 | SR 55 (US 19) Placement of Asphalt Base vs. Optional Base Groups 4 & 5 | A |
| | | | |
6/27/05 | 25873415201 | 20445 | SR 56/ I-75 Interchange - Global Claim Issues (13 Issues) | A |
5/2/00 | 25873415201 | 20445 | SR 56/ I-75 Interchange - Delay Due to Pile Splices | A |
| | | | |
5/31/05 | 25705015201 | T7033 | SR 688 (Ulmerton Road) - Payment for Fittings
DRB Clarification | A |
2/7/05 | 25866715201 | T7020 | SR 93A (I-75) Granite Shortage, Replace Pavement Markings, MOT Devices (3 Issues) | A |
12/27/04 | 40371315201 | T7041 | SR-45 (Nebraska Ave) Lane Closure Restrictions | A |
10/15/04 | 4057515201 | E7A90 | Bridge Painting Hillsborough/Pinellas Co.
(Weather Days) | R |
10/11/04 | 25583415201 | T7004 | SR 674 - Granite Shortage, Extra Work S-10 & S-10a, Abnormal Weather (3 Issues) | A |
| | | | |
6/4/04 | 25633715201 | 21591 | SR 54 - Weather Related Damage, Elevated Water Table | A |
6/4/04 | 25633715201 | 21591 | SR 54 - Loading & Hauling Muck Materials for Ponds 3 East & 3 West | A |
6/4/04 | 25633715201 | 21591 | SR 54 - Existing Asphalt Thickness/Loss of Use of Limerock Material | A |
| | | | |
5/6/04 | 25638715201 | 21491 | SR 52 - Seeding & Mulching Payment | A |
1/7/04 | 25716315201 | 21563 | SR 44 (US41 to CR 470) Additional Dewatering due to Differing Site Conditions | A |
| | | | |
11/21/03 | 25480515201 | 20358 | SR 50 & SR 45 - Time Adjustment due to Delays from Tampa Port Security | A |
11/21/03 | 25480515201 | 20358 | SR 50 & SR 45 - Time Extension & Adjustment for Concrete Work/Driveway Over-runs | A |
11/21/03 | 25480515201 | 20358 | SR 50 & SR 45 - Unforeseen Work Associated w/ Pavement Failures on US 41 | R |
4/4/03 | 25480515201 | 20358 | SR 50 & SR 45 - Subsoil Excavation Under Pipes | A |
10/21/02 | 25480515201 | 20358 | SR 50 & SR 45 - Significant Change in Work (JPA Fittings, Water & Force Mains) | A |
2/29/00 | 25480515201 | 20358 | SR 50 & SR 45 - Sanitary Sewer Bypass Pumping | A |
| | | | |
9/23/03 | 25709315201 | 21362 | SR 60 (Memorial Causeway) Storm Water Run-Off | A |
8/27/03 | 40371815201 | 21674 | SR 45 (US 41) Timely Submittal of Claims for Subgrade Testing; Non Standard Construction; Sod Overrun | A |
8/18/03 | 25573415201 | 21274 | SR 45 (Causeway Blvd) Sanitary Sewer Revision/Relocation | A |
| | | | |
7/21/03 | 25886115201 | 20489 | SR 93 (I-275) Replacement Cost for High Mast Lighting Conduit Conflict at Ramp D1 | A |
1/29/02 | 25886115201 | 20489 | SR 93 (I-275) Slab Replacement/Joint Sealing | A |
| | | | |
3/31/03 | 25633815201 | 21198 | SR 54 (from SR 55 to East of Madison St.) Plan Issue - Fiberglass Structure in Pond 1A | A |
4/4/02 | 25633815201 | 21198 | SR 54 (from SR 55 to East of Madison St.) Modification of Incentive Completion Dates | A |
| | | | |
3/3/03 | 25709515201 | 20857 | SR 55 (US 19) Request for Additional Time Due to Utility Conflicts | A |
6/6/00 | 25690515201 | 20752 | SR 679 (Bunces Pass Bridge) Sheet Piling Installed at Bridge Approaches | A |
6/2/00 | 25683115201 | 20287 | SR 586 (Curlew Road) Utility Conflict | A |
5/22/00 | 25841015201 | 20573 | SR 93 (I-275) Joint Sealing Around Replacement Slabs | A |
| | | | |
4/25/00 | 25846315201 | 19566 | SR 400 (I-4) Barrier Wall Out of Tolerance | A |
4/25/00 | 25846315201 | 19566 | Significant Change to Pile Installation | A |
4/25/00 | 25846315201 | 19566 | SR 400 (I-4) Bridge Barrier Wall | A |
4/25/00 | 25846315201 | 19566 | SR 400 (I-4) Poor Finish on Bridge Deck | R |
8/24/98 | 25846315201 | 19566 | SR 400 (I-4) Jack & Bore Issues (Pay Items, Tunneling, Plan Error Delays) | A |
| | | | |
8/6/97 | 25846015201 | 19126 | SR 400 (I-4) Untimely Notice of Intent to File Claim for Traffic Accident Repairs (Issue #12) | A |
7/11/97 | 25846015201 | 19126 | SR 400 (I-4) Temporary Sheet Piling Placed in Baker Canal (Issue # 11) | A |
7/11/97 | 25846015201 | 19126 | SR 400 (I-4) Partial Payment for Temporary Items (Issue # 10) | A |
6/11/97 | 25846015201 | 19126 | SR 400 (I-4) Payment for Granular Backfill Behind MSE Wall (Issue # 9) | A |
4/16/97 | 25846015201 | 19126 | SR 400 (I-4) Removal of Existing Median Barrier (Issue # 8) | A |
4/6/97 | 25846015201 | 19126 | SR 400 (I-4) Typical Wall Sections Bond Breaker (Issue # 7) | A |
7/3/96 | 25846015201 | 19126 | SR 400 (I-4) Pay Item for Alternate Base | A |
5/24/96 | 25846015201 | 19126 | SR 400 (I-4) Payment for Smooth Outer Wall Concrete Pipe (Issue # 5) | A |
4/19/96 | 25846015201 | 19126 | SR 400 (I-4) Maintenance of Highway/Overhead Sign Lighting | A |
4/19/96 | 25846015201 | 19126 | SR 400 (I-4) Cost of Maintaining Guardrail | A |
3/6/96 | 25846015201 | 19126 | SR 400 (I-4) Plan Quantities of Guardrail | A |
| | | | |
5/16/96 | 25553315201 | 18734 | SR 600 (US 92) End Block Beam Reinforcing Steel (VECP Modified Beams) | A |
2/26/96 | 25553315201 | 18734 | SR 600 (US 92) Delays to Statnamic Testing (Failure to Document Claim) | A |
1/23/96 | 25553315201 | 18734 | SR 600 (US 92) Removal of Obstructions from Drilled Shafts | R |
| | | | |
8/12/95 | 25828415201 | 18703 | Clearwater Pass Bridge - Plans Interpretation - Conduit in Pedestrian Barrier Wall | A |
4/17/95 | 25828415201 | 18703 | Clearwater Pass Bridge - Laitance of Drilled Shaft Concrete - Remedial Work at Pier 4 | A |
| | | | |
| | | A = Accepted, P = Partial Acceptance, R = Rejected | |