Date | FIN# | Contract | Subject | A/R/P |
5/14/19 | 22044275201 | T3543 | Design-Build S.R. 87 from 2miles South of Yellow River Bridge To C.R. 184 (4-lane and Bridge in Santa Rosa County
| A
|
12/9/17 | 21860565201 | E3O54 | SR 10 (9-Mile Road) from CR 99 Beulah Rd to SR 297 Pine Forest Rd | R |
10/18/17 | 22066425201 | E3L23 | SR 83 (US 331) Choctawhatchee Bay & Relief Bridge Additions | R |
5/1/17 | 22077295201 | E3K68 | SR Multi-Lane Improvements, Washington & Holmes County | A |
4/3/17 | 42450815201 | T3416 | SR 10 (US90) over Yellow River (Bridge No. 570004) | R |
11/10/16 | 22044275201 | T3543 | Design‐Build S.R. 87 from 2miles South of Yellow River Bridge To C.R. 184
| A
|
10/11/16 | 41110225201 | T3471 | SR 123, Segment 2 - Claim #1 Additional Compensation for Hauling | R |
3/7/15 | 42893915201 | T3467 | Leon County, I-10, Resurfacing, Borrow Issue | A |
3/13/12 | 40716715201 | T3089 | SR 79 (Holmes Creek Bridge) - Damaged Piles, Utility Conduit, Shaft Wall Collapse (6 issues) | A |
2/22/12 | 42163515201 | T3294 | SR 61 (US 27) - Extra Work Placing Asphalt in Gutter (Quantum Ruling) | A |
8/28/10 | 22041265201 | T3311 | SR 281 (Avalon Blvd.) - Erosion Control/Drainage System Issues | A |
2/25/10 | 42016115201 | E3G67 | SR 8/I-10; Cleaning & Painting Steel Columns & Partial Pile Jacket Removal (Bridges 550050 & 550089) | A |
| | | | |
1/15/08 | 41747425201 | E3E19 | Design-Build Bridge Replacement I-10; Grinding & Grooving of Bridge Decks (Quantum Ruling) | A |
12/11/07 | 41747425201 | E3E19 | Design-Build Bridge Replacement I-10; Grinding & Grooving of Bridge Decks in Regards to Contract Provision 5-12.3 | A |
8/28/07 | 41747425201 | E3E19 | Design-Build Bridge Replacement I-10; Grinding & Grooving of Bridge Decks | |
9/14/06 | 41747425201 | E3E19 | SR 8/I-10, Escambia Bay Bridge Replacement - Compensation for Temporary Barrier Wall | A |
| | | | |
6/11/07 | 22044255201 | T3043 | SR 87 - Time Extension for Gas Main Relocation | A |
2/13/06 | 22044255201 | T3043 | SR 87 - Additional Contract Days Due to Impact of Hurricane Katrina | A |
| | | | |
6/17/05 | 40621415201 | E3A03 | SR 30/US 98 (Hathaway Bridge Replacement) - Award of Contract Time as Excusable Delays | R |
| | | | |
11/11/04 | 22040215201 | 21556 | SR 87 - Placement of Guardrail Pedestrian Safety Treatment Pipe Rail | A |
5/14/03 | 22040215201 | 21556 | SR 87 - Impacts and Delay Damages due to Utility Relocation | |
| | | | |
1/29/04 | 21980415201 | 20943 | Claim Package Submitted by SANDCO, Inc. (6 Claim & 7 Final Estimate Issues) | A |
8/1/02 | 22064215201 | 20944 | SR 30/US 98 - Mack Bayou Wetland Delay Claim | R |
| | | | |
6/16/00 | 21978215201 | 20159 | SR 366 - Failure to Perform Timely Density Tests (No Documentation of Damage) | A |
6/13/00 | 21978215201 | 20159 | SR 366 - Utility Conflict (High Voltage Pole) | A |
| | | | |
5/10/00 | 21993915201 | 19197 | SR 20 (Apalachicola River Bridge) - Payment for Repair of Expansion Joints | |
| | | | |
10/10/97 | 22276615201 | E3720 | I-10 Bridge Replacement - Pile Length, Preformed Pile Holes, & Bridge Jacking Payment | |
2/20/97 | 22276615201 | E3720 | I-10 Bridge Replacement over Blackwater Bay - Changed Site Conditions | |
| | | | |
| | | A = Accepted, P = Partial Acceptance, R = Rejected | |