Chap./Sect.
| Revised Date
| Title
|
5.16 | 8/22/2024 | Earthwork Notes & Documentation |
11.6 | 8/22/2024 | Documentation for Multi-Fin Projects, Under One Contract |
2.2 | 5/31/2024 | Final Estimates Pre-Planning |
6.2 | 5/31/2024 | Alternative Contracts |
8.2 | 5/31/2024 | Environmental Permit Compliance |
8.12 | 5/31/2024 | Locally Funded Agreements |
8.14 | 5/31/2024 | Value Added Features |
3.1 | 5/31/2024 | Preconstruction Conference |
5.6 | 5/31/2024 | Utility Work |
5.11 | 5/31/2024 | Final Estimates Documents |
5.12 | 5/31/2024 | Final As-Built Plans Process |
5.13 | 5/31/2024 | Plan Summary Boxes/ Estimated Quantities Report |
5.14 | 5/31/2024 | Field Records and Contractor's Certifications |
5.15 | 5/31/2024 | Final Measurements |
5.16 | 5/31/2024 | Earthwork Notes & Documentation |
11.3 | 5/31/2024 | Categorizing Asphalt & Other Base Courses |
11.4 | 5/31/2024 | Asphalt Adjustments |
11.6 | 5/31/2024 | Documentation for Multi-Fin Projects, Under One Contract |
11.7 | 5/31/2024 | Asphalt Construction Information for CQC |
5.7 | 7/26/2023 | Federal Aid Project Requirements |
3.5 | 5/17/2023 | Final Estimates Quality Reviews |
11.1 | 4/28/2023 | Asphalt Lot Documentation |
11.9 | 4/28/2023 | Salvage of Materials |
11.7 | 2/17/2023 | Asphalt Construction Information For Contractor Quality Control |
5.8 | 1/31/2023 | Control of Materials |
3.2 | 1/31/2023 | Quality Assurance & Quality Control of Field Operations |
12.1 | 12/2/2022 | Project Acceptance |
7.4 | 12/2/2022 | Contingency Supplemental Agreements and Work Orders |
7.3 | 12/2/2022 | Supplemental Agreements and Unilateral Payments |
7.2 | 12/2/2022 | Time Extensions |
5.1 | 9/12/2022 | Project Diary |
12.1 | 7/7/2022 | Project Acceptance |
7.4 | 7/7/2022 | Contingency Supplemental Agreement and Work Orders |
7.6 | 6/3/2022 | Contracting For Governor Declared Emergencies |
7.2 | 4/21/2022 | Time Extensions |
7.3 | 5/25/22 | Supplemental Agreements and Unilateral Payments |
8.10 | 4/20/22 | Monitoring Existing Structures and Noise Abatement |
8.9 | 4/14/22 | Contract Termination |
8.5 | 4/1/22 | Contract Delinquency |
6.1 | 3/29/22 | Unpaid Bills Processing |
3.4 | 3/7/22 | Dispute Review Board |
11.1 | 1/5/22 | Asphalt LOT Documentation |
3.3 | 12/2/21 | Contractor's Quality Control Plan |
5.8 | 12/2/21 | Control of Materials |
8.11 | 9/27/21 | Contractor Initiated Submittals |
4.1 | 9/27/21 | Administration of Consultant CEI Contracts |
5.9 | 7/21/21 | Process Review of Construction Engineering & Inspection |
11.3 | 8/2/21 | Categorizing Asphalt & Other Base Courses |
7.5 | 7/15/21 | Construction Contract Claims |
7.7 | 7/9/21 | Payment of Recovery of Property Damage Costs |
1.3 | 7/9/21 | Pre-Bid Questions and Answers |
1.1 | 7/9/21 | Plans Review and Comments |
11.5 | 4/9/21 | Testing & Correcting Asphalt Pavement Surface Deficiencies |
5.10 | 4/9/21 | Verification Inspection & Testing |
11.2 | 4/9/21 | Asphalt Mix Temperature Control |
13.3 | 4/21/21 | Contractor Survey |
3.5 | 4/7/21 | Quality Assurance Reviews for Final Estimates |
5.3 | 3/10/21 | Subletting of Contract |
13.1 | 3/10/21 | Contractor's Past Performance Rating |
12.1 | 2/26/21 | Project Acceptance |
3.1 | 2/18/21 | Preconstruction Conference |
8.3 | 2/5/21 | Operation Within Railroad Right of Way |
5.5 | 2/10/21 | Equipment Rental |
5.2 | 2/9/21 | Contractor Vehicle Registration |
5.1 | 12/23/20 | Project Diary |
1.2 | 12/15/20 | Contract Duration & Alternative Contracting Techniques |
9.1 | 10/30/20 | Maintenance Of Traffic |
2.1 | 9/11/20 | Project Scheduling |
10.2 | 8/11/20 | Prestressed/Precast Concrete Components |
10.11 | 8/7/20 | General Structures Construction Issues |
8.13 | 6/25/20 | Pipe Inspection, Evaluation and Repair |
8.4 | 7/15/20 | Shop & Erection Drawing Process |
10.6 | 7/15/20 | Underwater Bridge Construction Inspection |
13.2 | 7/14/20 | Constructability Grades |
10.7 | 6/19/20 | Post Tensioned Bridges |
10.9 | 6/19/20 | Structural Steel & Miscellaneous Metal Components |
10.3 | 6/3/20 | Concrete Construction |
7.2 | 6/3/20 | Time Extensions |
7.6 | 5/19/20 | Contracting for Governor Declared Emergencies |
10.10 | 4/30/20 | Bridge Construction Issues that Must Involve Office of Construction Staff |
10.8 | 4/27/20 | Auger Cast Piles |
10.12 | 4/27/20 | Foundations on Design-Build Projects |
10.5 | 4/8/20 | Drilled Shafts |
10.1 | 3/27/20 | Piles |
6.2 | 2/25/20 | Alternative Contracts |
8.7 | 2/11/20 | Contractor Non-Responsibility For Construction Contract |
8.6 | 2/11/20 | Contract Default |
6.1 | 1/27/20 | Unpaid Bills Processing |
7.3
| 10/28/19 | Supplemental Agreements and Unilateral Payments |
7.4
| 8/15/19 | Contingency Supplemental Agreements, Work Orders
|
3.2
| 7/17/19 | Quality Assurance and Quality Control of Field Construction Operations
|
11.9
| 6/13/19 | Salvage of Materials
|
12.1
| 9/27/18 | Project Acceptance |
4.2 | 8/27/18 | Consultant CEI Accountability |
10.4 | 8/21/18 | Coatings & Asbestos Removal, Handling & Disposal & Structural Steel Coating Issues |
9.3 | 6/5/18 | Work Zone Traffic Incident Evaluation and Reporting |
5.4 | 3/13/18 | Contract Wage Requirements |
10.9 | 12/19/17 | Structural Steel & Miscellaneous Metal Components |
11.8 | 12/7/17 | Submittals |
3.5 | 12/1/07 | Final Estimates Quality Reviews |
11.2 | 8/24/17 | Asphalt Mix Temperature Control |
10.2 | 4/19/17 | Precast Prestressed Concrete Components |
11.5 | 4/19/17 | Testing and Correcting Asphalt Pavement Surface Deficiencies |
6.1 | 2/13/17 | Unpaid Bills Processing |
Introduction | 1/23/17 | Introduction |
9.2 | | Work Zone Regulatory Speeds (Deleted) |
5.1 | 12/4/13 | F.A.I.N. Resolution Project Diary |
TOC | 1/24/13 | Table of Contents |
4.1 | 11/2/12 | Administration of Contract Time |
4.2 | 11/2/12 | Construction Contract Time Extension Procedure |