Chap./Sect. Revised Date Title
2.1 12/21/18 Project Scheduling
8.3 12/6/18 Operation Within Railroad Right of Way
6.2 11/30/18 Alternative Contracts
10.9 11/30/18 Structural Steel & Miscellaneous Metal Components
8.12
11/29/18 Locally Funded Agreements
13.1 11/1/18 Contractor's Past Performance Rating
12.1 9/27/18 Project Acceptance
10.7 9/17/18 Post Tensioned Bridges
2.2 9/12/18 Final Estimates Pre-Planning
10.3 8/29/18 Concrete Construction
4.1 8/27/18 Administration of Consultant CEI Contracts
4.2 8/27/18 Consultant CEI Accountability
10.4 8/21/18 Coatings & Asbestos Removal, Handling & Disposal & Structural Steel Coating Issues
10.6 8/21/18 Underwater Bridge Construction Inspection
8.4 8/21/18 Shop & Erection Drawing Process
8.11 7/11/18 Contractor Initiated Submittals
8.13 6/20/18 Pipe Inspection, Evaluation and Repair
8.2 6/20/18 Environmental Permit Compliance
8.14 6/20/18 Value Added Features
5.11 6/20/18 Final Estimates Documents
10.12 6/20/18  Foundations on Design-Build Projects
9.3 6/5/18 Work Zone Traffic Incident Evaluation and Reporting
10.8 6/1/18 Auger Cast Piles
10.5 6/1/18 Drilled Shafts
7.2 5/18/18 Time Extensions
8.10 5/16/18 Noise and Vibration Abatement
5.16 5/16/18 Earthwork Notes & Documentation
10.1 5/16/18 Piles
8.9 4/9/18 Contract Termination
8.7 4/9/18 Contractor Non-Responsibility For Construction Contract
8.6 3/21/18 Contract Default
8.5 3/21/18 Contract Delinquency
7.5 3/20/18 Construction Contract Claims
13.1 3/13/18 Contractor's Past Performance Rating
5.4 3/13/18 Contract Wage Requirements
6.1 3/1/18 Unpaid Bills Processing
5.14 2/13/18 Field Records
1.2 1/30/18 Contract Duration & Alternative Contracting Techniques
10.9 12/19/17 Structural Steel & Miscellaneous Metal Components
5.7 12/20/17 Federal Aid Project Requirements
13.3 12/19/17 Contractor Survey
5.8 12/12/17 Control of Materials
11.8 12/7/17 Submittals
11.1 12/7/17 Asphalt LOT Documentation
7.6 12/7/17 Contracting for Governor Declared Emergencies
3.5 12/1/07 Final Estimates Quality Reviews
5.12 11/29/17 Final As-Built Plans Process
11.4 10/30/17 Adjustments
11.9 10/30/17 Salvage of Materials
3.3 10/25/17 Contractor's Quality Control Plan
3.1 10/4/17 Preconstruction Conference
5.3 9/29/17 Subletting of Contract
7.3 9/29/17 Supplemental Agreements and Unilateral Payments
7.4 9/28/17 Contingency Supplemental Agreements, Work Orders
5.2 9/28/17 Contractor Vehicle Registration
5.5 9/28/17 Equipment Rental
5.15 9/28/17 Final Measurements
9.1 9/27/17 Maintenance Of Traffic
13.2 9/27/17 Constructability Grades
11.5 9/27/17 Testing & Correcting Asphalt Pavement Surface Deficiencies
8.12 8/9/17 Locally Funded Agreements
3.2 8/21/17 Quality Assurance and Quality Control of Field Construction Operations
11.2 8/24/17 Asphalt Mix Temperature Control
5.10 8/21/17 Verification Inspection & Testing
7.7 8/7/17 Payment of Recovery of Property Damage Costs
11.3 8/21/17 Categorizing Asphalt & Other Base Courses
1.1 6/27/17  Plans Review and Comments
10.11 8/7/17 General Structures Construction Issues
5.9 7/19/17 Process Review of Construction Engineering & Inspection
6.2 6/24/17 Alternative Contracts
5.13 6/14/17 Plan Summary Boxes
11.6 6/14/17 Documentation for Multi-Fin Projects, Under One Contract
11.7 6/14/07 Asphalt Construction Information for CQC
10.2 4/19/17 Precast Prestressed Concrete Components
10.10 4/19/17 Bridge Construction Issues that Must Involve Office of Construction Staff
11.5 4/19/17 Testing and Correcting Asphalt Pavement Surface Deficiencies
1.3 4/3/17 Pre-Bid Questions and Answers
6.1 2/13/17 Unpaid Bills Processing
12.1 2/15/17 Project Acceptance
Introduction 1/23/17 Introduction
3.3 12/28/16 Contractor's Quality Control Plan
8.13 12/15/16 Pipe Inspection, Evaluation & Repair
5.11 12/19/16 Final Estimates Documents
5.6 10/27/16 Utility Work
3.5 6/12/2016 Quality Assurance Reviews for Final Estimates
13.3 3/18/16 Contractor Survey
10.2 10/6/14 Prestressed/Precast Concrete Componenets
9.2 Work Zone Regulatory Speeds (Deleted)
11.2 2/4/14 Asphalt Mix Temperature Control Density Earthwork Inspection Training Program
5.1 12/4/13 F.A.I.N. Resolution Project Diary
TOC 1/24/13 Table of Contents
4.1 11/2/12 Administration of Contract Time
4.2 11/2/12 Construction Contract Time Extension Procedure