Chap./Sect.
Revised Date
Title
7.65/19/20Contracting for Governor Declared Emergencies
8.115/7/20Contractor Initiated Submittals
5.75/12/20Federal Aid Project Requirements
10.104/30/20Bridge Construction Issues that Must Involve Office of Construction Staff
10.84/27/20Auger Cast Piles
10.124/27/20Foundations on Design-Build Projects
7.54/15/20Construction Contract Claims
5.64/14/20Utility Work
13.24/14/20Constructability Grades
2.24/8/20Final Estimates Pre-Planning
10.54/8/20Drilled Shafts
11.44/6/20Adjustments
10.13/27/20Piles
8.123/16/20Locally Funded Agreements
8.93/9/20Contract Termination
5.122/13/20Final As-Built Plans Process
6.22/25/20Alternative Contracts
8.72/11/20Contractor Non-Responsibility For Construction Contract
8.62/11/20Contract Default
6.11/27/20Unpaid Bills Processing
8.51/27/20Contract Delinquency
3.1
11/1/2019Preconstruction Conference
3.3
10/29/19Contractor's Quality Control Plan
7.3
10/28/19Supplemental Agreements and Unilateral Payments
5.11
10/18/19Final Estimates Documents
5.810/3/19Control of Materials
5.169/30/19Earthwork Notes & Documentation
9.1 9/12/19Maintenance Of Traffic
11.59/11/19Testing & Correcting Asphalt Pavement Surface Deficiencies
3.48/26/19Dispute Review Board
7.4
8/15/19Contingency Supplemental Agreements, Work Orders
11.1
8/15/19Asphalt LOT Documentation
3.2
7/17/19Quality Assurance and Quality Control of Field Construction Operations
5.14
7/17/19Field Records
7.7
7/11/19Payment of Recovery of Property Damage Costs
13.3
7/9/19Contractor Survey
5.3
7/9/19Subletting of Contract
5.10
6/25/19Verification Inspection & Testing
11.2
6/25/19Asphalt Mix Temperature Control
11.3
6/19/19Categorizing Asphalt & Other Base Courses
5.156/19/19Final Measurements
1.3
6/18/19Pre-Bid Questions and Answers
5.2
6/17/19Contractor Vehicle Registration
11.9
6/13/19Salvage of Materials
5.135/7/19Plan Summary Boxes
5.9
5/8/19Process Review of Construction Engineering & Inspection
11.6
4/25/19Documentation for Multi-Fin Projects, Under One Contract
11.7
4/25/19Asphalt Construction Information for CQC
1.1
4/22/19Plans Review and Comments
3.54/16/19Quality Assurance Reviews for Final Estimates
5.5
4/9/19Equipment Rental
13.14/8/19Contractor's Past Performance Rating
10.21/30/19Prestressed/Precast Concrete Componenets
10.111/30/19General Structures Construction Issues
2.112/21/18Project Scheduling
8.312/6/18Operation Within Railroad Right of Way
10.911/30/18Structural Steel & Miscellaneous Metal Components
12.19/27/18Project Acceptance
10.79/17/18Post Tensioned Bridges
10.38/29/18Concrete Construction
4.18/27/18Administration of Consultant CEI Contracts
4.28/27/18Consultant CEI Accountability
10.48/21/18Coatings & Asbestos Removal, Handling & Disposal & Structural Steel Coating Issues
10.68/21/18Underwater Bridge Construction Inspection
8.48/21/18Shop & Erection Drawing Process
8.136/20/18Pipe Inspection, Evaluation and Repair
8.26/20/18Environmental Permit Compliance
8.146/20/18Value Added Features
5.116/20/18Final Estimates Documents
9.36/5/18Work Zone Traffic Incident Evaluation and Reporting
7.25/18/18Time Extensions
5.165/16/18Earthwork Notes & Documentation
5.43/13/18Contract Wage Requirements
1.21/30/18Contract Duration & Alternative Contracting Techniques
10.912/19/17Structural Steel & Miscellaneous Metal Components
11.812/7/17Submittals
3.512/1/07Final Estimates Quality Reviews
8.128/9/17Locally Funded Agreements
11.28/24/17Asphalt Mix Temperature Control
6.26/24/17Alternative Contracts
10.24/19/17Precast Prestressed Concrete Components
11.54/19/17Testing and Correcting Asphalt Pavement Surface Deficiencies
6.12/13/17Unpaid Bills Processing
12.12/15/17Project Acceptance
Introduction1/23/17Introduction
3.312/28/16Contractor's Quality Control Plan
8.1312/15/16Pipe Inspection, Evaluation & Repair
9.2 Work Zone Regulatory Speeds (Deleted)
5.112/4/13F.A.I.N. Resolution Project Diary
TOC1/24/13Table of Contents
4.111/2/12Administration of Contract Time
4.211/2/12Construction Contract Time Extension Procedure