Design-Build Boiler-Plate

July - December 2017


The Design-Build Boilerplate* is the Division I Master Document to be used in the Request for Proposal (RFP) for Design-Build projects.


Design Build Pick-List

NOTE: The files below contain optional text which may be incorporated into
the Design-Build Boilerplate to create specific Contract language.

File Title Usage Notes
To Change Award and Execution Time
SP0030200 Award and Execution of Contract When necessary to change standard "Award and Execution"
Design Build Finance
SP0030600DBF Execution of Contract and Bond Use on Design Build Finance projects
Award and Execution of Contract - Public Records
SP0030900D1-717 Public Records All Projects in District 1
SP0030900D2-717 Public Records All Projects in District 2
SP0030900D3-717 Public Records All Projects in District 3
SP0030900D4-717 Public Records All Projects in District 4
SP0030900D5-717 Public Records All Projects in District 5
SP0030900D6-717 Public Records All Projects in District 6
SP0030900D7-717 Public Records All Projects in District 7
SP0030900TP-717 Public Records All Turnpike Enterprise Projects
Structures Over 1500 Feet in Length (over water)
SP0050901 Inspection Long bridge jobs (1500 feet or longer); modify to suit
Toll Facility
SP0070201TP-717 Permits and Licenses (No free passes will be issued to the Contractor for use on the Toll Facility) All Jobs with Toll Facilities.
Toll Facility
SP0071101-Tolls Preservation of Property for Toll Facilities. Use with approval of the District Traffic Operations Engineer.
Operations Within Railroad Right-of-Way
SP0071104RR Operations within Railroad Right-of-Way Use on Projects involving CSX Transportation, FEC, South Florida Rail Corridor and the Central Florida Rail Corridor.
Utilities - Florida Gas Transmission Company
SP0071105FGT Projects Involving Florida Gas Transmission Company Use on Projects involving Florida Gas Transmission Company (FGT).
SP0071201FGTDB Projects Involving Florida Gas Transmission Company with Encroachment Agreements Use on Projects involving Florida Gas Transmission Company (FGT) with Encroachment Agreements. Must be used with SP0071105FGT.
Legal Requirements and Responsibility to the Public
SP0072700 Equal Employment Opportunity Requirements All Non-Federal Aid Projects
SP0072800 Preference to State Residents All Non-Federal Aid Projects
SP0072900 Legal Requirements and Responsibility to the Public - E-Verify All Projects
SP0073000 Legal Requirements and Responsibility to the Public - Scrutinized Companies All Projects
SP0073100 Legal Requirements and Responsibility to the Public - Title VI Assurance - DOT 1050.2A, Appendix A and Appendix E All Federal Aid Projects
Liquidated Damages for Tolls
SP0081000 Prosecution and Progress - Amount of Liquidated Damages Use on revenue producing projects.
Partnering
SP0080306 Prosecution of Work - Partnering 999-16
Disputes Review Board
SP0080307RDRB Regional Disputes Review Board Jobs without Pay Item No. 999-20
Jobs with Lighting
SP0080409 Contaminated Material - Mercury-Containing Devices and Lamps Jobs with lighting.
Damage Recovery
SP0081300 Damage Recovery Use when requested by the District Construction Engineer.
Alternative Bidding
SP0081300A Prosecution and Progress All Jobs with Alternative Bidding. Use with the approval of the District Construction Engineer.
SP0081300B "Bonus" Payment and Waiver of Contractor Claims - Date Specific Bonus (Date Specific) Use with the approval of the District Construction Engineer.
SP0081300BCD "Bonus" Payment and Waiver of Contractor Claims - Calendar Day Bonus (Calendar Days) Use with the approval of the District Construction Engineer.
SP0081300ID Incentive - Disincentive Incentive - Disincentive. Use with the approval of the District Construction Engineer.
SP0081300LQS Liquidated Savings for Early Completion Liquidated Savings. Use with the approval of the District Construction Engineer.
SP0081300MB "Bonus" Payment and Waiver of Contractor Claims - Milestone Milestone Bonus. Use with the approval of the District Construction Engineer. Do not use with SP00813000B or SP0081300BCD.
SP0081300MID Incentive - Disincentive - Milestone Milestone Incentive - Disincentive. Use with the approval of the District Construction Engineer.. Do not use with SP0081300ID)

 

Design Build Attachments to the RFP

 

DIVISION II CHANGES
SP1010000DB Mobilization Use on all Design Build Projects.
SP1050813DB Contractor Quality Control General Requirements Use when Geotechnical Services are required for the project.
SP4550000DB Structures Foundations Use when Geotechnical Services are required for the project.
VALUE ADDED DEVELOPMENTAL SPECS
DEV475 Value Added Bridge Components Use when requested and approved by the District Construction Engineer.