Chapter/Section Revised Date Title
Table of Contents 1/24/13  
Introduction 1/23/2017  
Introduction II 1/1/13 Final Estimates Process DELETED 7/7/14
   
Chapter 1   PRE-LETTING ACTIVITIES
Chapter 1 TOC   Table of Contents
1.1 4/22/19 Plans Review and Comments
1.2 1/30/18 Constructability/Biddability Reviews
Contract Duration & Alternative Contracting Techniques
1.3 6/18/19 Pre-Bid Questions & Answers
     
Chapter 2   Office Preparation
Chapter 2 TOC   Table of Contents
2.1 12/21/18 Project Scheduling
2.2 9/12/18 Final Estimates Pre-Planning
     
Chapter 3   Preconstruction activities
Chapter 3 TOC   Table of Contents
3.1 3/7/19 Preconstruction Conference Partial Payment for Certain Materials
3.2 7/17/19 Quality Assurance & Quality Control of Field Operations
3.3 10/25/17 Contractor's Quality Control Plan  Unpaid Bills Processing
3.4 7/1/11 Dispute Review Boards
3.5 4/19/19 Final Estimates Quality Reviews
     
Chapter 4   Consultant CEI Management
Chapter 4 TOC   Table of Contents
4.1 8/27/18 Administration of Contract Time Suspension of Contract Time
4.2 8/27/18 Construction Contract Time Extension Procedure
     
Chapter 5   project documentation
Chapter 5 TOC 3/11/10 Table of Contents
5.1 Pen & Ink 12/4/13 F.A.I.N. Resolution  Project Diary
5.2 6/17/19 Contractor Vehicle Registration Environmental Commitment Compliance
5.3 7/9/19 Subletting of Contract
5.4 3/13/18 Operation Within Railroad Right of Way Contract Wage Requirements
5.5 4/9/19 Equipment Rental
5.6 3/8/19 Utility Work
5.7 12/20/17 Experimental Application - Dissemination of Information Federal-Aid Project Requirements
5.8 12/12/17 Control of Materials
5.9 5/8/19 Process Review of Construction Engineering & Inspection
5.10 6/25/19 Verification Inspection & Testing
5.11 6/20/18  Final Estimates Documents
5.12 11/29/17 Final "As-Built" Plans Process
5.13 5/7/19 Computation Books
5.14 7/16/19 Field Records
5.15 6/19/19 Final Measurements
5.16 5/16/18 Earthwork Notes & Documentation
     
Chapter 6   contract payments
Chapter 6 TOC   Table of Contents
6.1 3/1/18 Maintenance of Traffic Unpaid Bills Processing
6.2 11/30/18 Alternative Contracts
     
Chapter 7   Contract Modifications
Chapter 7 TOC 5/15/08 Table of Contents
7.1   Contractor's Past Performance Report
7.2 5/18/18 Time Extensions
7.3 8/15/19 Supplemental Agreements & Unilateral Payments
Post Award Plans and Contract Changes
7.4 8/15/19 Contingency Supplemental Agreements, Work Orders/Field Supplemental Agreements
7.5 3/20/18 Construction Contract Claims
7.6 12/7/17  Contracting For Governor Declared Emergencies
7.7 7/11/19 Payment of Recovery of Property Damage Costs
     
Chapter 8   administrative requirements
Chapter 8 TOC 5/11/09 Table of Contents
8.2 6/20/18 Environmental Permit Compliance
8.3 12/6/18 Operation Within Railroad Right-of-Way
8.4 8/21/18 Shop & Erection Drawing Process
8.5 3/21/18 Contract Delinquency
8.6 3/21/18 Contract Default
8.7 4/9/18 Contractor Non-Responsibility For Construction Contract
8.8 4/13/10 State Arbitration Board
8.9 4/9/18 Contract Termination
8.10 5/16/18 Noise & Vibration Abatement
8.11 7/11/18 Contractor Initiated Submittals
8.12 8/9/17 Locally Funded Agreements
8.13 6/20/18  Pipe Inspection, Evaluation & Repair
8.14 6/20/18 Value Added Features
Chapter 9   Maintenance of traffic
     
Chapter 9 TOC   Table of Contents
9.1 9/27/17 Maintenance of Traffic (MOT)
9.2   Work Zone Regulatory Speeds (Deleted)
9.3 6/5/18 Work Zone Traffic Incident Evaluation and Reporting
     
Chapter 10   Structures
Chapter 10 TOC 5/1109 Table of Contents
10.1 5/16/18 Piles Pile Lengths
10.2 1/30/19 Straight-edging and Correction of Surface Deficiencies on Last Asphalt Layer Prior to the Friction Course  Prestressed/Precast Concrete Components
10.3 8/29/18 Concrete Construction Rejection of Asphalt Mix Based on Temperature
10.4 8/21/18 Coatings Paint & Asbestos Removal, Handling & Disposal & Structural Steel Coating Issues
10.5 6/1/2018 Drilled Shafts
10.6 8/21/18 Mass Concrete Underwater Bridge Construction Inspection
10.7 9/17/18 Post Tensioned Bridges
10.8 6/1/2018 Auger Cast Piles
10.9 11/30/18 Structural Steel & Miscellaneous Metal Components
10.10 1/31/19 Bridge Construction Issues
10.11 1/30/19 General Structures Construction Issues
10.12 6/20/18 Foundations on Design-Build Projects
     
CHAPTER 11   ASPHALT
Chapter 11 TOC 9/3/13 Table of Contents
11.1 8/15/19 Asphalt LOT Documentation
11.2 6/25/19 Asphalt Mix Temperature Control
Density Earthwork Inspection Training Program
11.3 6/19/19 CATEGORIZING ASPHALT & OTHER BASE COURSES
11.4 10/30/17  Adjustments
11.5 9/27/17  Testing & Correcting Asphalt Pavement Surface Deficiencies
11.6 4/25/19 Documentation for Multi-Fin Projects, Under One Contract
11.7 4/25/19 Asphalt Construction Information for CQC Specifications
11.8 12/7/17 Submittals
11.9 6/13/19 Salvage of Materials
     
Chapter 12   Project Closeout
Chapter 12 TOC   Table of Contents
12.1 9/27/18 Project Acceptance
     
Chapter 13   Performance Ratings
Chapter 13 TOC   Table of Contents
13.1 4/8/19 Contractor's Past Performance Rating
13.2 9/27/17 Constructability Grades
13.3 7/9/19 Contractor Survey