Chapter/SectionRevised DateTitle
Table of Contents1/24/13 
Introduction1/23/2017 
Introduction II1/1/13Final Estimates Process DELETED 7/7/14
   
Chapter 1 PRE-LETTING ACTIVITIES
Chapter 1 TOC Table of Contents
1.14/22/19Plans Review and Comments
1.21/30/18Constructability/Biddability Reviews
Contract Duration & Alternative Contracting Techniques
1.36/18/19Pre-Bid Questions & Answers
   
Chapter 2 Office Preparation
Chapter 2 TOC Table of Contents
2.112/21/18Project Scheduling
2.24/8/20Final Estimates Pre-Planning
   
Chapter 3 Preconstruction activities
Chapter 3 TOC Table of Contents
3.111/1/19Preconstruction Conference Partial Payment for Certain Materials
3.27/17/19Quality Assurance & Quality Control of Field Operations
3.310/29/19Contractor's Quality Control Plan  Unpaid Bills Processing
3.48/26/19Dispute Review Boards
3.54/19/19Final Estimates Quality Reviews
   
Chapter 4 Consultant CEI Management
Chapter 4 TOC Table of Contents
4.18/27/18Administration of Contract Time Suspension of Contract Time
4.28/27/18Construction Contract Time Extension Procedure
   
Chapter 5 project documentation
Chapter 5 TOC3/11/10Table of Contents
5.1 Pen & Ink12/4/13F.A.I.N. Resolution  Project Diary
5.26/17/19Contractor Vehicle Registration Environmental Commitment Compliance
5.37/9/19Subletting of Contract
5.43/13/18Operation Within Railroad Right of Way Contract Wage Requirements
5.54/9/19Equipment Rental
5.64/14/20Utility Work
5.75/12/20Experimental Application - Dissemination of Information Federal-Aid Project Requirements
5.810/3/19Control of Materials
5.95/8/19Process Review of Construction Engineering & Inspection
5.106/25/19Verification Inspection & Testing
5.1110/18/19Final Estimates Documents
5.122/13/20Final "As-Built" Plans Process
5.135/7/19Computation Books
5.147/16/19Field Records
5.156/19/19Final Measurements
5.165/16/18Earthwork Notes & Documentation
   
Chapter 6 contract payments
Chapter 6 TOC Table of Contents
6.11/27/20/Maintenance of Traffic Unpaid Bills Processing
6.22/25/20Alternative Contracts
   
Chapter 7 Contract Modifications
Chapter 7 TOC5/15/08Table of Contents
7.1 Contractor's Past Performance Report
7.25/18/18Time Extensions
7.310/28/19Supplemental Agreements & Unilateral Payments
Post Award Plans and Contract Changes
7.48/15/19Contingency Supplemental Agreements, Work Orders/Field Supplemental Agreements
7.54/15/20Construction Contract Claims
7.612/7/17 Contracting For Governor Declared Emergencies
7.77/11/19Payment of Recovery of Property Damage Costs
   
Chapter 8 administrative requirements
Chapter 8 TOC5/11/09Table of Contents
8.26/20/18Environmental Permit Compliance
8.312/6/18Operation Within Railroad Right-of-Way
8.48/21/18Shop & Erection Drawing Process
8.51/27/20Contract Delinquency
8.62/11/20Contract Default
8.72/11/20Contractor Non-Responsibility For Construction Contract
8.84/13/10State Arbitration Board
8.93/9/20Contract Termination
8.105/16/18Noise & Vibration Abatement
8.115/7/20Contractor Initiated Submittals
8.123/16/20Locally Funded Agreements
8.136/20/18 Pipe Inspection, Evaluation & Repair
8.146/20/18Value Added Features
Chapter 9 Maintenance of traffic
   
Chapter 9 TOC Table of Contents
9.19/12/19Maintenance of Traffic (MOT)
9.2 Work Zone Regulatory Speeds (Deleted)
9.36/5/18Work Zone Traffic Incident Evaluation and Reporting
   
Chapter 10 Structures
Chapter 10 TOC5/1109Table of Contents
10.13/27/20Piles Pile Lengths
10.21/30/19Straight-edging and Correction of Surface Deficiencies on Last Asphalt Layer Prior to the Friction Course  Prestressed/Precast Concrete Components
10.38/29/18Concrete Construction Rejection of Asphalt Mix Based on Temperature
10.48/21/18Coatings Paint & Asbestos Removal, Handling & Disposal & Structural Steel Coating Issues
10.54/8/20Drilled Shafts
10.68/21/18Mass Concrete Underwater Bridge Construction Inspection
10.79/17/18Post Tensioned Bridges
10.84/27/20Auger Cast Piles
10.911/30/18Structural Steel & Miscellaneous Metal Components
10.104/30/20Bridge Construction Issues
10.111/30/19General Structures Construction Issues
10.124/27/20Foundations on Design-Build Projects
   
CHAPTER 11 ASPHALT
Chapter 11 TOC9/3/13Table of Contents
11.18/15/19Asphalt LOT Documentation
11.26/25/19Asphalt Mix Temperature Control
Density Earthwork Inspection Training Program
11.36/19/19CATEGORIZING ASPHALT & OTHER BASE COURSES
11.44/6/20Adjustments
11.59/11/19Testing & Correcting Asphalt Pavement Surface Deficiencies
11.64/25/19Documentation for Multi-Fin Projects, Under One Contract
11.74/25/19Asphalt Construction Information for CQC Specifications
11.812/7/17Submittals
11.96/13/19Salvage of Materials
   
Chapter 12 Project Closeout
Chapter 12 TOC Table of Contents
12.19/27/18Project Acceptance
   
Chapter 13 Performance Ratings
Chapter 13 TOC Table of Contents
13.14/8/19Contractor's Past Performance Rating
13.24/14/20Constructability Grades
13.37/9/19Contractor Survey