January 2013 Workbook

Program Management

Implemented Modifications to the 2013 Standard Specifications

January 2013 Workbook

for Lettings Effective January - June 2013


Special Provisions - Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.

Supplemental Specifications - Additions or revisions to the Standard Specifications.

History of Revisions - To review the History of revisions for this Workbook.

Mandatory Revisions - Critical modifications implemented for the Workbook.
     Mandatory Revision #5 - To review the implementation letter.
     Mandatory Revision #4 - To review the implementation letter.
     Mandatory Revision #3 - To review the implementation letter.
     Mandatory Revision #2 - To review the implementation letter.
     Mandatory Revision #1 - To review the implementation letter.

Workbook Document - Final - To review the changes to the Workbook.
Workbook Document - Draft - To review the Workbook.


Note: These files are in Adobe Acrobat (PDF) format.

File size ranges from 9 kb to 279 kb.


SPECIAL PROVISIONS SP0000001 All Jobs
EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF WORK.
(REV 7-5-12) (7-26-12) (1-13)

Insert Information Required.
Change(s) to: 2-4.
SP0020400 All Jobs, (add a phone number or e-mail address)
PREPARATION OF PROPOSALS.
(REV 6-22-04) (FA 7-13-04) (1-05)

Change(s) to: 2-5.1.
SP0020501AB A+B Bidding. Use with the approval of the Chief Engineer.
Use with SP0030100AB, SP0030203AB,SP0081300AB and SP0080701AB
PREPARATION OF PROPOSALS.
(REV 2-21-05) (FA 3-31-05) (1-06)

Insert Information Required.
Change(s) to: 2-5.1.
SP0020501LR Lane Rental. Use with the approval of the Chief Engineer.
Use with SP0030100LR, SP0081300LR and SP0081300LRDR
CONSIDERATION OF BIDS - SCOPE ALTERNATES.
(REV 2-15-07) (7-07)

Change(s) to: 3-1.
SP0030001 Use with proper authority.
Notify Contracts Office on Transmittal Memo.
AWARD AND EXECUTION OF CONTRACT.
(REV 11-5-97) (FA 1-20-98) (7-00)

Insert Information Required
Change(s) to: 3-1.
SP0030100AB A+B Bidding. Use with the approval of the Chief Engineer.
Use with SP0020501AB, SP0030203AB,SP0080701AB and SP0081300AB
BUDGETARY CONSTRAINTS.
(REV 9-26-06) (FA 10-6-06) (1-07)

Insert Information Required
Change(s) to: 3-1.
SP0030100BC Use with proper authority.
Notify the Contracts Administration Office on the Transmittal Memo.
AWARD AND EXECUTION OF CONTRACT.
(REV 5-5-11) (10-20-11) (7-12)

Change(s) to: 3-1, 3-2.2, 3-5.1.
SP0030100DC District Let Construction Contracts less than $250,000 and
all Maintenance Contracts, excluding Lump Sum
AWARD AND EXECUTION OF CONTRACT.
(REV 4-11-97) (FA 5-7-97) (7-00)

Change(s) to: 3-1.
SP0030100LR Lane Rental. Use with the approval of the Chief Engineer.
Use with SP0020501LR, SP0081300LR and SP0081300LRDR
AWARD AND EXECUTION OF CONTRACT.
(REV 8-1-00) (1-01)

Change(s) to: 3-1.
SP0030100LS Lump Sum Projects
AWARD AND EXECUTION OF CONTRACT.
(REV 7-26-01) (7-10)

Insert Information Required
Change(s) to: 3-2, 3-6, 3-7.
SP0030200 When necessary to change standard “Award and Execution”
Contracts Office must approve.
AWARD OF CONTRACTS - A+B BIDDING
(REV 8-22-96) (FA 9-3-96) (1-10)

Insert Information Required
Change(s) to: 3-2.
SP0030203AB A+B Bidding. Use with the approval of the Chief Engineer.
Use with SP0020501AB, SP0030100AB,SP0080701AB and SP0081300AB
SCOPE OF THE WORK - INTENT OF CONTRACT.
(REV 8-19-09) (FA 8-24-09) (1-10)

Insert Information Required.
Change(s) to: 4-1.
SP0040100 All Jobs, excluding Lump Sum.
Do not use with SP0040100SLPQ.
SCOPE OF THE WORK.
(REV 8-24-10) (FA 10-8-10) (7-11)

Insert Information Required.
Change(s) to: 4-1, 4-3.1, 4-3.4, 4-3.9.4.
SP0040100LS All Lump Sum Projects.
Do not use with SP0040100SLLS.
SCOPE OF THE WORK - INTENT AND SCOPE.
(REV 8-24-10) FA 10-8-10) (7-11)

Insert Information Required.
Change(s) to: 4-14-3.1, 4-3.4, 4-3.9.4.
SP0040100SLLS All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Lump Sum. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0040100LS.
SCOPE OF THE WORK - INTENT AND SCOPE.
(REV 9-16-09) (FA 11-9-09) (7-10)

Insert Information Required.
Change(s) to: 4-1, 4-3.1, 4-3.4, 4-3.9.4.
SP0040100SLPQ All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Plan Quantity. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0040100.
UNFORESEEABLE WORK.
(REV 9-28-98) (1-10)

Change(s) to: 4-4.
SP0040400 999-25
CONTROL OF THE WORK.
(REV 3-15-02) (1-13)

Change(s) to: 5-1.1, 5-2, 5-7.6.
SP0050501LS Lump Sum Projects
INSPECTION.
(REV 2-10-94) (1-13)

Insert Information Required.
Change(s) to: 5-9.1
SP0050901 Long bridge jobs (1500 feet or longer); modify to suit
CONTROL OF MATERIALS.
(REV 8-17-09) (FA 8-24-09) (1-10)

Change(s) to: 6-1.
SP0060100LS Lump Sum Projects
CONTROL OF MATERIALS - SOURCE OF SUPPLY - STEEL.
(REV 10-19-12) (1-13)

Change(s) to: 6-5.2.
SP0060502 All Jobs (Mandatory #2)
REQUIREMENTS FOR FEDERAL JOBS - COMPLIANCE WITH FHWA 1273.
(REV 7-16-12) (8-2-12) (1-13)
Change(s) to: 7-1.1.
SP0070101 All Federal Aid Jobs
PERMITS PROCURED BY THE DEPARTMENT.
(REV 8-7-01) (FA 4-14-05) (1-10)

Change(s) to: 7-2.1.
SP0070201A Jobs with permit(s) procured by DOT
DISCHARGE TO OR WORK OR STRUCTURES IN NAVIGABLE WATERS OF THE U.S., WATERS OF THE U.S. AND WATERS OF THE STATE.
(REV 7-16-09) (FA 7-30-09) (1-10)

Change(s) to: 7-2.2.
SP0070202 When DEP Generic Permit is required
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC.
(REV 8-22-12) (1-13)

Insert Information Required.
Change(s) to: 7-7.1, 7-13.2, 7-13.3.
SP0070701DC District Let Contracts less than $250,000 and all Maintenance Contracts.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - OPERATIONS WITHIN RAILROAD RIGHT-OF-WAY.
(REV 11-5-10) (FA 11-9-10) (7-11)

Change(s) to: 7-11.5.
SP0071105 Projects Involving CSX Transportation.
UTILITY WORK.
(REV 2-10-94) (1-10)

Change(s) to: 7-11.6.3.
SP0071163A When there are no utility work schedules
UTILITY SCHEDULES.
(REV 8-27-01) (FA 4-14-05) (1-10)

Change(s) to: 7-11.6.3.
SP0071163B When there are utility work schedules
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WAGE RATES FOR FEDERAL-AID PROJECTS.

(REV 12-21-09) (FA 12-28-09) (7-10) Insert Information Required.
Change(s) to: 7-16.
SP0071600 All Federal Aid Jobs
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - DISADVANTAGED BUSINESS ENTERPRISE PROGRAM.
(REV 10-23-12) (1-13)

Change(s) to: 7-24.
SP0072400 All Jobs (Mandatory #2)
EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS.
(REV 4-25-02) (FA 7-17-02) (1-10)

Change(s) to: Section 7-26.
SP0072600 Non-Federal Aid Projects
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PREFERENCE TO STATE RESIDENTS.
(REV 6-15-10) (9-10)

Change(s) to: Section 7.
SP0072700 Non-Federal Aid Projects - Construction Projects Only
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - E-VERIFY.
(REV 6-13-11) (FA 6-16-11) (8-11)

Change(s) to: Section 7.
SP0072800 All Jobs
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - SCRUTINIZED COMPANIES.
(REV 6-17-11) (7-11)

Change(s) to: Section 7.
SP0072900 All Jobs
SUBMISSION OF WORKING SCHEDULE.
(REV 1-11-11) (FA 5-12-11) (1-12)

Change(s) to: 8-3.2.
SP0080302A Use only when CPM is authorized by District Construction Engineer. Do not use with SP0080302DC.
PROSECUTION AND PROGRESS.
(REV 6-18-12) (1-13)

Change(s) to: 8-3.2, 8-8, 8-9.1.
SP0080302DC District Let Construction Contracts (including Lump Sum) less than $250,000,

and all Maintenance Contracts. Do not use with SP0080302A.

PROSECUTION OF WORK - FLEXIBLE START TIME.
(REV 2-15-10) (FA 2-17-10) (7-10)

Insert Information Required
Change(s) to: 8-3.3.
SP0080303A When called for by the District Construction Engineer.
*Contracts Office must be notified.
BEGINNING WORK.
(REV 7-10-95) (1-10)

Insert Information Required
Change(s) to: 8-3.3.
SP0080303B When called for by the District Construction Engineer. Use with the approval of the Chief Engineer.
BEGINNING WORK.
(REV 10-22-98) (11-5-98) (1-10)

Insert Information Required.
Change(s) to: 8-3.3.
SP0080303C Only when called for by the District Construction Engineer. Use with the approval of the Chief Engineer.
*Contracts Office must be notified.
PROSECUTION OF WORK - PARTNERING.
(REV 5-5-12) (FA 5-21-12) (1-13)

Insert Information Required.
Change(s) to: 8-3.3.
SP0080306 999-16*
*Contracts Office must be notified
PROSECUTION OF WORK - DISPUTES REVIEW BOARD.
(REV 1-4-11) (FA 1-21-11) (7-11)

Change(s) to: 8-3.
SP0080307DRB 999-20 Items
Contracts Office must be notified
PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD.
(REV 1-4-11) (FA 1-21-11) (7-11)

Change(s) to: 8-3.
SP0080307RDRB Jobs without 999-20 Items
PROSECUTION OF WORK - STATEWIDE DISPUTES REVIEW BOARD.
(REV 1-4-11) (FA 1-21-11) (7-11)

Change(s) to: 8-3.
SP0080308SDRB 334, 337, 350, 570, 580 or 649 Items.
PROSECUTION AND PROGRESS.
(REV 8-1-00) (1-10)

Change(s) to: 8-4.1, 8-7.3.1.
SP0080401LS Lump Sum Projects
LIMITATIONS OF OPERATIONS - FENCING.
(REV 6-17-04) (FA 7-13-04) (1-10)

Change(s) to: 8-4.8.
SP0080408 Jobs on Limited Access Highways
CONTAMINATED MATERIAL - MERCURY-CONTAINING DEVICES AND LAMPS.
(REV 11-6-95) (FA 12-27-95) (7-11)

Insert Information Required.
Change(s) to: 8-4.9.
SP0080409 Jobs with Lighting*
COMPUTATION OF CONTRACT TIME.
(REV 12-22-98) (FA 1-19-99) (1-10)

Insert Information Required.
Change(s) to: 8-7.1.
SP0080701A Use when requested by proper authority, (must be modified)
COMPUTATION OF CONTRACT TIME.
(REV 7-24-96) (FA 9-3-96) (1-10)

Change(s) to: 8-7.1.
SP0080701AB A+B Bidding. Use with the approval of the Chief Engineer. Use with SP0020501AB, SP0030100AB,SP0030203AB and SP0081300AB
COMPUTATION OF CONTRACT TIME.
(REV 2-14-94) (1-10)

Insert Information Required.
Change(s) to: 8-7.1.
SP0080701B Use with the approval of the Chief Engineer.
COMPUTATION OF CONTRACT TIME.
(REV 12-22-98) (FA 2-1-99) (1-10)

Change(s) to: 8-7.1.
SP0080701C Use when requested by the District Construction Engineer.
DAMAGE RECOVERY.
(REV 2-4-04) (1-10)

Insert Information Required.
Change(s) to: Section 8.
SP0081300 Use when requested by the District Construction Engineer. (Do not use with Lane Rental)
PROSECUTION AND PROGRESS.
(REV 7-28-97) (1-10)

Change(s) to: Section 8.
SP0081300A All Jobs with Alternative Bidding. Use with the approval of the Chief Engineer.
8-13. Incentive - Disincentive for A+B.
(REV 7-27-04) (FA 7-28-04) (1-13)

Insert Information Required.
Change(s) to: 8-13.
SP0081300AB A+B Bidding. Use with the approval of the Chief Engineer. Use with SP0020501AB, SP0030100AB, SP0030203AB and SP0080701AB
8-13. "Bonus" Payment and Waiver of Contractor Claims.
(REV 5-19-04) (FA 7-13-04) (1-05)

Insert Information Required.
Change(s) to: 8-13.
SP0081300ABB A+B Jobs with Bonus Use with the approval of the Chief Engineer.
8-13. " Bonus " Payment and Waiver of Contractor Claims.
(REV 7-27-04) (FA 7-28-04) (1-05)

Insert Information Required.
Change(s) to: 8-13.
SP0081300B Bonus (Date Specific) Use with the approval of the Chief Engineer.
8-13. "Bonus" Payment and Waiver of Contractor Claims.
(REV 7-27-04) (FA 7-28-04) (1-05)

Insert Information Required.
Change(s) to: 8-13.
SP0081300BCD Bonus (Calendar Days) Use with the approval of the Chief Engineer.
8-13. Incentive - Disincentive.
(REV 7-27-04) (FA 7-28-04) (1-05)

Insert Information Required.
Change(s) to: 8-13.
SP0081300ID Incentive - Disincentive. Use with the approval of the Chief Engineer. Do not use with SP0081300MID.
8-13. Incentive - Disincentive for Lane Rental Days.
(REV 9-25-03) (FA 12-24-03) (7-04)

Insert Information Required.
Change(s) to: 8-13.
SP0081300IDLR Incentive-Disincentive for Lane Rental Days. Use with the approval of the Chief Engineer. Do not use with SP0081300LR or SP0081300LRDR
8-13. Liquidated Savings for Early Completion.
(REV 5-18-99) (FA 6-10-99) (7-00)

Insert Information Required.
Change(s) to: 8-13.
SP0081300LQS Liquidated Savings. Use with the approval of the Chief Engineer.
8-13. Pay Adjustment For Fewer-More Lane Rental Days.
(REV 4-29-97) (FA 5-7-97) (7-00)

Insert Information Required.
Change(s) to: 8-13.
SP0081300LR Lane Rental. Use with the approval of the Chief Engineer. Use with SP0020501LR, SP0030100LR and SP0081300LRDR.
8-13. Damage Recovery.
(REV 9-25-03) (FA 12-24-03) (7-04)

Insert Information Required.
Change(s) to: 8-13.
SP0081300LRDR Lane Rental. Use with the approval of the Chief Engineer. Use with SP0020501LR, SP0030100LR and SP0081300LR.
8-13. "Bonus" Payment and Waiver of Contractor Claims.
(REV 4-12-06) (FA 4-25-06) (1-07)

Insert Information Required.
Change(s) to: 8-13.
SP0081300MB Milestone Bonus Use with the approval of the Chief Engineer. Do not use with SP0081300B or SP0081300BCD
8-13. Incentive - Disincentive.
(REV 2-9-06) (FA 4-25-06) (1-07)

Insert Information Required.
Change(s) to: 8-13.
SP0081300MID Milestone Incentive-Disincentive. Use with the approval of the Chief Engineer. Do not use with SP0081300ID
MEASUREMENT AND PAYMENT.
(REV 12-14-11) (FA 1-5-12) (7-12)

Change(s) to: 9-1.3, 9-2, 9-3, 9-5.5.2, 9-9, 9-11.
SP0090103LS Lump Sum Projects. Do not use with SP0090103SLLS.
MEASUREMENT AND PAYMENT.
(REV 2-7-13) (4-13)

Change(s) to: 9-1.3, 9-2, 9-3, 9-5.1, 9-8.1, 9-9.
SP0090103SLLS All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Lump Sum. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0090103LS. MANDATORY 4
MEASUREMENT AND PAYMENT.
(REV 2-7-13) (4-13)

Change(s) to: 9-1.3.2, 9-2, 9-3.2.3, 9-5.1, 9-8.1, 9-9, 9-11.
SP0090103SLPQ All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Plan Quantity. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0090501DC. MANDATORY 4
MEASUREMENT AND PAYMENT.
(REV 10-29-08) (FA 1-16-09) (1-10)

Change(s) to: 9-5.1, 9-5.4, 9-9.
SP0090501DC District Let Contracts. Excluding Lump Sum Projects. Do not use with SP0090103SLPQ.
MAINTENANCE OF TRAFFIC.
(REV 9-4-12) (FA 9-6-12) (1-13)

Change(s) to: 102-13.12.
SP1021312 102-89-17 Items
ENGINEER'S FIELD OFFICE.
(REV 1-4-11) (FA 2-17-11) (1-12)

Change(s) to: 109.
SP1090000 109-71 Items
REMOVAL OF EXISTING STRUCTURES - STRUCTURES TO BE REMOVED.
(REV 9-10-07) (FA 2-15-08) (1-10)

Insert Information Required.
Change(s) to: 110-6.1.
SP1100601 Use when requested by proper authority (Must have signed agreement with Local Agency).
REMOVAL OF EXISTING STRUCTURES.
(REV 5-13-05) (FA 8-18-05) (1-10)

Change(s) to: 110-6.6.
SP1100606 Use when areas of Asbestos Abatement are identified in the Plans
MATERIAL FOR REEF ESTABLISHMENT.
(REV 7-10-95) (FA 6-21-99) (1-10)

Change(s) to: 110-11.2, 110-12.7.
SP1101102 110-84
EXCAVATION - INDENTIFIED AREAS OF CONTAMINATION.
(REV 1-3-94) (FA 6-21-99) (1-10)

Change(s) to: 120-1.
SP1200100A Use when contaminated areas are delineated in the plans
EXCAVATION AND EMBANKMENT - ACCEPTANCE PROGRAM
(REV 9-16-09) (FA 11-9-09) (7-10)

Change(s) to: 120-10.3.1.
SP1201003SL All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use.
EXCAVATION FOR STRUCTURES AND PIPE - ACCEPTANCE PROGRAM
(REV 9-16-09) (FA 11-9-09) (7-10)

Change(s) to: 125-9.3.1.
SP1250903SL All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use.
STABILIZING - ACCEPTANCE PROGRAM
(REV 9-16-09) (FA 11-9-09) (7-10)

Change(s) to: 160-4.2.4.
SP1600402SL All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use.
PREDESIGNED STABILIZED SUBGRADE.
(REV 3-12-07) (FA 3-14-07) (1-10)

Change(s) to: 161.
SP1610000 Non-Traffic and Shoulder-Only Construction. Do Not Use on Widening Projects
ROCK BASE - ACCEPTANCE PROGRAM
(REV 9-16-09) (FA 11-9-09) (7-10)

Change(s) to: 200-7.2.2
SP2000702SL All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use.
GRADED AGGREGATE BASE.
(REV 8-8-07) (1-10)

Change(s) to: 204.

SP2040000 Non-FA Jobs with 285 Items
MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 8-31-99) (FA 2-14-00) (1-10)

Insert Information Required.
Change(s) to: 327-1, 327-6.
SP3270100 When the plans provide a location for stockpiling milled material.Insert quantity to be retained. Use all, tons, cubic yards
MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 12-1-93) (1-10)

Change(s) to: 327-2.
SP3270200 Use when requested by districts
PORTLAND CEMENT CONCRETE - ACCEPTANCE SAMPLING AND TESTING.
(REV 6-25-10) (FA 7-8-10) (1-11)

Change(s) to: 346-9.2.
SP3460902SL All Projects less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use.
Structures Foundations - Dynamic Testing WITHOUT Test Piles.
(REV 6-26-12) (7-12)

Change(s) to: 455-1 through 455-12.
SP4550100DTwoTP Projects with 100% Dynamic Testing of Pile Foundations WITHOUT Test Piles.
Structures Foundations - Dynamic Testing WITH Test Piles.
(REV 6-26-12) (7-12)

Change(s) to: 455-1 through 455-12.
SP4550100DTwTP Projects with 100% Dynamic Testing of Pile Foundations WITH Test Piles.
INTEGRAL PILE JACKETS.
(REV 11-16-11) (FA 12-8-11) (7-12)

Change(s) to: 457.
SP4570000 457 Items
STRUCTURAL STEEL AND MISCELLANEOUS METALS.
(REV 1-25-12) (7-12)

Change(s) to: 460-7.2, 460-8.8.
SP4600702 460 Items
CRASH CUSHIONS.
(REV 8-4-11) (FA 8-9-11) (1-12)

Change(s) to: 544-4.
SP5440400 544-75-1AA Items
LANDSCAPE INSTALLATION.
(REV 3-15-13) (4-13)

Change(s) to: 580-2.
SP5800200 All Federal Aid Jobs (Mandatory #5)
MOTORIST AID CALL BOX RELOCATION.
(REV 8-24-10)  (1-11)

Change(s) to: 714.
SP7140000 714-1-500
TRAFFIC MONITORING SITE VEHICLE SENSOR (CLASS II).
(REV 1-3-12) (FA 1-27-12) (7-12)

Change(s) to: 741.
SP7410000 741-1 Items
TRAFFIC MONITORING SITE VEHICLE SPEED/CLASSIFICATION UNIT.
(REV 6-16-99) (FA 7-20-99) (1-10)

Change(s) to: 743.
SP7430000 743-70 Items
TRAFFIC MONITORING SITE SOLAR POWER UNIT.
(REV 10-22-10) (FA 11-22-10) (7-11)

Change(s) to: 744.
SP7440000 744-70 Items
TRAFFIC MONITORING SITE INDUCTIVE LOOP ASSEMBLY.
(REV 6-22-10) (FA 11-22-10) (7-11)

Change(s) to: 745.
SP7450000 745-70 Items
TRAFFIC MONITORING SITE CABINET.
(REV 5-6-08) (FA 10-14-08) (1-10)

Change(s) to: 746.
SP7460000 746-7A-BCD
TRAFFIC MONITORING SITE MODEM.
(REV 5-20-99) (FA 7-20-99) (1-10)

Change(s) to: 747.
SP7470000 747-70 Items
GENERAL REQUIREMENTS FOR THE EVALUATION OF TRAFFIC MONITORING SITE EQUIPMENT AND MATERIALS.
(REV 5-12-99) (FA 7-20-99) (1-10)

Change(s) to: 748.
SP7480000 Jobs with Traffic Monitoring Sites
STRUCTURAL COATING MATERIALS.
(REV 1-25-12) (7-12)

Change(s) to: 975-6.1.
SP9750601 460 Items
 
Supplemental Specifications SS0000001 All Jobs
005       CONTROL OF THE WORK.
(REV 12-16-11) (1-13)

Change(s) to: 005.
SS0050000 All Jobs (Mandatory #3)
102       MAINTENANCE OF TRAFFIC.
(REV 10-9-12) (1-13)

Change(s) to: 102.
SS1020000 All Jobs (Mandatory #1)
346       PORTLAND CEMENT CONCRETE.
(REV 10-9-12) (1-13)

Change(s) to: 346.
SS3460000 All Jobs (Mandatory #1)
347       PORTLAND CEMENT CONCRETE - CLASS NS.
(REV 10-9-12) (1-13)

Change(s) to: 347.
SS3470000 All Jobs (Mandatory #1)
400       CONCRETE STRUCTURES.
(REV 10-9-12) (1-13)

Change(s) to: 400.
SS4000000 All Jobs (Mandatory #1)
425       INLETS, MANHOLES, AND JUNCTION BOXES.
(REV 10-9-12) (1-13)

Change(s) to: 425.
SS4250000 All Jobs (Mandatory #1)
TECHNICAL SPECIAL PROVISIONS.

The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package.

 Insert # ________

TSPs Jobs with TSPs