EMERGENCY INFORMATION FDOT Emergency Travel Alert:  For information on the current situation, please visit the following page - Alerts.

Construction

Office of Construction / Publications / CPAM

CPAM Redline History

Picture of a Florida Roadway
Chapter/SectionRevised DateTitle
Table of Contents1/24/13 
Introduction1/23/2017 
Introduction II1/1/13Final Estimates Process DELETED 7/7/14
  
Chapter 1 PRE-LETTING ACTIVITIES
Chapter 1 TOC Table of Contents
1.176/27/17Plans Review and Comments
1.21/30/18Constructability/Biddability Reviews
Contract Duration & Alternative Contracting Techniques
1.34/3/17Pre-Bid Questions & Answers
   
Chapter 2 Office Preparation
Chapter 2 TOC Table of Contents
2.13/11/11Project Scheduling
2.29/12/18Final Estimates Pre-Planning
   
Chapter 3 Preconstruction activities
Chapter 3 TOC Table of Contents
3.110/4/17 Preconstruction Conference Partial Payment for Certain Materials
3.28/21/17 Quality Assurance & Quality Control of Field Operations
3.310/25/17Contractor's Quality Control Plan  Unpaid Bills Processing
3.47/1/11Dispute Review Boards
3.512/1/17Final Estimates Quality Reviews
   
Chapter 4 Consultant CEI Management
Chapter 4 TOC Table of Contents
4.18/27/18Administration of Contract Time Suspension of Contract Time
4.28/27/18Construction Contract Time Extension Procedure
   
Chapter 5 project documentation
Chapter 5 TOC3/11/10Table of Contents
5.1 Pen & Ink12/4/13F.A.I.N. Resolution  Project Diary
5.29/28/17Contractor Vehicle Registration Environmental Commitment Compliance
5.39/29/17Subletting of Contract
5.43/13/18Operation Within Railroad Right of Way Contract Wage Requirements
5.59/28/17Equipment Rental
5.610/27/16 Utility Work
5.712/20/17Experimental Application - Dissemination of Information Federal-Aid Project Requirements
5.812/12/17Control of Materials
5.97/19/17Process Review of Construction Engineering & Inspection
5.108/21/17Verification Inspection & Testing
5.116/20/18 Final Estimates Documents
5.1211/29/17Final "As-Built" Plans Process
5.136/14/17Computation Books
5.142/13/18Field Records
5.159/28/17Final Measurements
5.165/16/18Earthwork Notes & Documentation
   
Chapter 6 contract payments
Chapter 6 TOC Table of Contents
6.13/1/18Maintenance of Traffic Unpaid Bills Processing
6.211/30/18Alternative Contracts
   
Chapter 7 Contract Modifications
Chapter 7 TOC5/15/08Table of Contents
7.1 Contractor's Past Performance Report
7.25/18/18Time Extensions
7.39/29/17Supplemental Agreements & Unilateral Payments
Post Award Plans and Contract Changes
7.49/28/17Contingency Supplemental Agreements, Work Orders/Field Supplemental Agreements
7.53/20/18Construction Contract Claims
7.612/7/17 Contracting For Governor Declared Emergencies
7.78/7/2017Payment of Recovery of Property Damage Costs
   
Chapter 8 administrative requirements
Chapter 8 TOC5/11/09Table of Contents
8.26/20/18Environmental Permit Compliance
8.312/6/18 Operation Within Railroad Right-of-Way
8.48/21/18Shop & Erection Drawing Process
8.53/21/18Contract Delinquency
8.63/21/18Contract Default
8.74/9/18Contractor Non-Responsibility For Construction Contract
8.84/13/10State Arbitration Board
8.94/9/18Contract Termination
8.105/16/18Noise & Vibration Abatement
8.117/11/18Contractor Initiated Submittals
8.1211/29/18Locally Funded Agreements
8.136/20/18 Pipe Inspection, Evaluation & Repair
8.146/20/18Value Added Features
Chapter 9 Maintenance of traffic
   
Chapter 9 TOC Table of Contents
9.19/27/17Maintenance of Traffic (MOT)
9.2 Work Zone Regulatory Speeds (Deleted)
9.36/5/18Work Zone Traffic Incident Evaluation and Reporting
   
Chapter 10 Structures
Chapter 10 TOC5/1109Table of Contents
10.15/16/18Piles Pile Lengths
10.24/19/2017Straight-edging and Correction of Surface Deficiencies on Last Asphalt Layer Prior to the Friction Course  Prestressed/Precast Concrete Components
10.38/29/18Concrete Construction Rejection of Asphalt Mix Based on Temperature
10.48/21/18Coatings Paint & Asbestos Removal, Handling & Disposal & Structural Steel Coating Issues
10.56/1/2018Drilled Shafts
10.68/21/18Mass Concrete Underwater Bridge Construction Inspection
10.79/17/18Post Tensioned Bridges
10.86/1/2018Auger Cast Piles
10.911/30/18Structural Steel & Miscellaneous Metal Components
10.104/19/17Bridge Construction Issues
10.118/7/17General Structures Construction Issues
10.126/20/18Foundations on Design-Build Projects
   
CHAPTER 11 ASPHALT
Chapter 11 TOC9/3/13Table of Contents
11.112/7/17Asphalt LOT Documentation
11.28/24/17Asphalt Mix Temperature Control
Density Earthwork Inspection Training Program
11.38/21/17CATEGORIZING ASPHALT & OTHER BASE COURSES
11.410/30/17 Adjustments
11.59/27/17 Testing & Correcting Asphalt Pavement Surface Deficiencies
11.66/14/17Documentation for Multi-Fin Projects, Under One Contract
11.76/14/17Asphalt Construction Information for CQC Specifications
11.812/7/17Submittals
11.910/30/17Salvage of Materials
   
Chapter 12 Project Closeout
Chapter 12 TOC Table of Contents
12.19/27/18Project Acceptance
   
Chapter 13 Performance Ratings
Chapter 13 TOC Table of Contents
13.111/1/18Contractor's Past Performance Rating
13.29/27/17Constructability Grades
13.312/19/17 Contractor Survey